14th March 2016- Deposit on land
16th April 2016- Initial deposit with Wisdom (for the Washington) $1000
22nd April 2016- Change to Majestic 35
7th June 2016- Tender Presentation and acceptance $5000
15th June 2016- Received revised tender
16th June 2016- Land registered
24th June 2016- Kitchen and Tile appointments
30th June 2016- Full payment of land
18th July 2016- Kitchen quote received and accepted
27th July 2016- Tile quote received and accepted
26th August 2016- Contract signing and 5% deposit
30th August 2016- Colours, landscape and electrical appointments
6th September 2016- Colour variations received
8th September 2016- NBN variation received
9th September 2016- Window variation received
13th September 2016- Landscape plans received
14th September 2016- File in administration
14th September 2016- Plans submitted to Developer
17th September 2016- Developer approves plans
17th September 2016- DA pack requested
20th September 2016- Provisional landscape quote received
5th October 2016- DA pack submitted to council
10th October 2016- Kitchen drawings received
27th October 2016- Neighbour notification period ends
1st November 2016- First communication with council regarding neighbour objection
6th December 2016- Notification of neighbours withdrawal of objection
9th December 2016- DA approval received
9th December 2016- Wrap up and DA assessment received
16th December 2016- Receive draft end panel
19th December 2016- Notify of errors with draft end panel
19th December 2016- Wisdom email corrected draft end panel
20th December 2016- Submit signed draft end panel after corrections
23rd December - 9th January 2017- Christmas shutdown
18th January 2017- Received final end panel and documentation
18th January 2017- Sent paperwork to bank for formal approval
15th February- Cleared land of dumped earth
16th February- Fences up
22nd February 2017- Formal approval received
1st March 2017- Letter of commencement received
2nd March 2017- File in Production estimating
4th March 2017- Portaloo delivered
7th March 2017- Aggregate delivered
11th March 2017- Site cut and fill
22nd March 2017- In construction officially
29th March 2017- Plumbing and piering complete
30th March 2017- waffle pods and steel delivered
31st March 2017-Commencement of formwork, waffle pods & steel
1st April 2017- Slab prep completed
4th April 2017-slab poured
11th April 2017- External plumbing installed
11th April 2017- Walk through with landscaping
21st April 2017- Frames delivered
21st April 2017- Backyard scraped